2014.03 WP10: Data Consumption Facilities Development Monthly Activity By Task and Beneficiary

From IMarine Wiki

(Difference between revisions)
Jump to: navigation, search
m (Created page with "Category:Restricted_Page {|align=right ||__TOC__ |} This WP10 Activity Report described the activities performed in '''March 2014''' by Beneficiary and Task. It is part of ...")
(NKUA Activities)
Line 11: Line 11:
=== NKUA Activities ===
=== NKUA Activities ===
-
''The beneficiary should report here a summary of the activities performed in the reporting period ''
+
* gCube Data Transformation Service transition into RESTful service has been completed. gDTS corresponding client libraries have been implemented.
 +
* Execution Engine Service has been split into three modules; one for clean installation, and two other carrying Search and DTS dependencies, for ease of deployment.
<xh4> Deviations and Corrective Actions </xh4>
<xh4> Deviations and Corrective Actions </xh4>
-
''The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.''
+
''none''
<xh4> Achievements </xh4>
<xh4> Achievements </xh4>
-
''The beneficiary should report here a bullet list highlighting the main achievements of the reporting period''
+
''none''
=== FORTH Activities ===
=== FORTH Activities ===

Revision as of 14:52, 11 April 2014

Contents

This WP10 Activity Report described the activities performed in March 2014 by Beneficiary and Task.

It is part of March 2014 Monthly Activity Report.

T10.1 Data Retrieval Facilities

NKUA Activities

  • gCube Data Transformation Service transition into RESTful service has been completed. gDTS corresponding client libraries have been implemented.
  • Execution Engine Service has been split into three modules; one for clean installation, and two other carrying Search and DTS dependencies, for ease of deployment.


none


none

FORTH Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

Terradue Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T10.2 Data Manipulation Facilities

Complete (the Task was active from M3 to M26 i.e. December 2013)

T10.3 Data Mining and Visualisation Facilities

Complete (the Task was active from M3 to M27 i.e. January 2014)

T10.4 Semantic Data Analysis Facilities

Complete (the Task was active from M4 to M27 i.e. January 2014)