T5.1 iMarine Data e-Infrastructure Operation

CERN Activities

CERN planned and followed the infrastructure upgrade to gCube 2.9.1 which fixed some production incidents. (https://portal.i-marine.d4science.org/web/guest/gcube-version)


The CNR infrastructure nodes have been moved to new IPs. Some issues have been found and properly fixed by CNR


Infrastructure upgrade to gCube 2.9.1

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T5.2 iMarine Data e-Infrastructure Nodes Provision

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

NKUA Activities

NKUA has been keeping up and running the provided nodes hosting GHNs, UMD and the gcube wiki. Nagios NRPE has been installed to all NKUA's nodes that are hosting GHNs, for central monitoring from CERN hosted Nagios.


none


  • Maintained the provided infrastructure operational
  • Maintained gcube wiki operational
  • Successfully installed Nagios NRPE plugin and the requested control commands

FAO Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FIN Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T5.3 iMarine Data Infrastructure Availability, Monitoring and Accounting

CERN Activities

Prepared the documentation for the installation of Nagios NRPE and Plugins on the D4science infra nodes (https://gcube.wiki.gcube-system.org/gcube/index.php/Monitoring_a_gCube_infrastructure_With_Nagios) . The installation and configuration have started, completed by NKUA on all production nodes. CERN hosted Nagios has been configured accordingly.

All messaging and accounting components ( except for portlets) have been moved to build with Maven.


None


None.