12.05.2014 Project Executive Board Conference Call
From IMarine Wiki
|
Agenda
Time: Monday May 12, 2014, 15:00 - 16:45 Europe/Rome
- On 9th TCom
- Short Summary of the activities performed in April 2014;
- assessment of the status of deliverables;
- assessment of the status of milestones;
- AOB.
Participants
TD | WP1 | WP2 | WP3 | WP4 | WP5 | WP6 | WP7 | WP8 | WP9 | WP10 | WP11 |
---|---|---|---|---|---|---|---|---|---|---|---|
P. Pagano | J.Michel / L. Nguyen | D. Castelli | A. Ellenbroek | S. Garavelli | P. Pagano (formerly A. Manzi) | L. Candela | P. Fabriani | P. Pagano | G. Coro | G. Gerbesiotis | G. Kakaletris |
Main Discussions and Actions
On 9th TCom
The target location is Crete and will be hosted by FORTH.
The time constraints are:
- FORTH can organise it for the last week of June, from 23rd on.
- there is a potential clash with the iMarine Board ... today or tomorrow this will be fixed;
- The TCom can be organised also in July, first two weeks;
- A final decision will be taken by the end of this week, after having fixed the dates for the iMarine Board meeting;
Other constraints/positions (almost all partners are out of travel budget):
- FAO has no possibility to phisically participate if the meeting is not organised in Rome;
- NKUA has no possibility to participate if the meeting will be organised in Rome, even in Athens (e.g. because of strikes);
- Crete is the most economic place;
- for CNR (they consumed the travel budget) it is cheaper to participate in a meeting in Crete than in Rome;
On April 2014 Activity Report
On WP1 Activity:
- The summary of April '14 activities;
- The final review date fixed and confirmed, it will be on Nov 25, 2014. The rehearsal is Nov 24;
- The final project event will be in September 17, 2014;
- A couple of effort report (for Jan and Feb) are sill missing, ERCIM will solicit the missing partners in the coming days;
- By end of June ERCIM will circulate an update picture of budget;
On WP2 Activity:
- The summary of April '14 activities;
- A news on VME-DB is planned, Anton will provide Sara with few lines on the event;
On WP3 Activity:
- The summary of April '14 activities;
- IRD interaction is a bit difficult, Anton is reporting problems in having information from them, the same is for WP6;
- they are potentially interested in biological enrichment facilities, however there is no concrete request yet;
- FAO will have a call with NATO colleagues, Anton can use the catalogues on the web site;
- if additional information is expected than we should make a try to complement this descriptive offering;
- On sustainability, a message to pass should be:
- infrastructure and its services will be offered for 2 years after the project end;
- Sara suggests that these aspects are discussed at the next SB and a clear statement on Sustainability be prepared for the web site;
- A number of experiments are ongoing by relying on the Statistical Manager, these should be published in the Wiki;
- FAO will prepare the Wiki page;
- CNR will modify the Wiki structure by adding something like "Experiments";
On WP4 Activity:
- The summary of April '14 activities;
- Webinars on openchannels.org should be organised, one in mid/late July and one in September;
- topic(s) should be selected and confirmation should be sent by Sara;
- On VRE portfolio, a draft of a potential document was created and circulated to Lino and Anton;
- the goal is to have a description that is not technical at all;
- if feedback is ready by end of this week then the document can be completed in a couple of weeks;
- On Final project event, the draft agenda will be defined by mid June;
- On iMarine Search Mobile App
- FAO will check the disclaimer;
- On ICRI Workshop
- it is ongoing
- ???
- it is ongoing
On WP5 Activity:
- The summary of April '14 activities;
- April represents the moth used to pass the duties from CERN to CNR and NKUA;
On WP6 Activity:
- The summary of April '14 activities;
On WP7 Activity:
- the summary of April '14 activities;
- No report has been produced;
- The TD will contact ENG for more information;
On WP10 Activity:
- The summary of April '14 activities;
On Deliverables
Status of deliverables is available via the dedicated Wiki page.
On Milestones
Status of milestones is available at a dedicated Wiki page
AOB
Next PEB conf call
Next PEB conf call is scheduled for June, 10th 15:00 -17:00 Rome time.