This WP10 Activity Report described the activities performed in November 2013 by Beneficiary and Task.
It is part of November Monthly Activity Report
T10.1 Data Retrieval Facilities
NKUA Activities
The activities of NKUA included:
- Bug fixing:
- Investigation and fix of problems related to Resource Registry that caused duplicate field resources.
- Index Enhancements:
- Investigation and design of the index rebuilding procedure for periodic updates with zero downtime (#2238).
- WikiDoc Validation:
None
None
FORTH Activities
The beneficiary should report here a summary of the activities performed in the reporting period
The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.
The beneficiary should report here a bullet list highlighting the main achievements of the reporting period
Terradue Activities
- Analysis of data sources supporting the Environmental enrichment, con'd
- None
- None
T10.2 Data Manipulation Facilities
NKUA Activities
The documentation of gCube Data Transformation Service has been validated successfuly (#1978).
none
- Update of gDTS Developer's Guide
CNR Activities
The beneficiary should report here a summary of the activities performed in the reporting period
The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.
The beneficiary should report here a bullet list highlighting the main achievements of the reporting period
FAO Activities
The beneficiary should report here a summary of the activities performed in the reporting period
The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.
The beneficiary should report here a bullet list highlighting the main achievements of the reporting period
T10.3 Data Mining and Visualisation Facilities
CNR Activities
CNR has worked on enhancements for the SM. In particular, the Interface is being transformed into a Widget to be used by other components #1297. Runtime resources are now invokable by the Ecological Engine library through the SM #1381. The files import facility has been designed and is in phase of implementation #2359. One major enhancement regards the transformation of Algorithms into Generic Resources #2258. Currently a new Generic Resource is generated for each algorithm and can be associated to different VREs.
On the algorithms development side, BiOnym has been implemented with a realization that follows the indications by Edward Vanden Berghe #2236. Furthermore a preliminary set of experiments has been made in the field of Common Species classification #2197. CNR also developed a facility to geo-spatialize tables and produce GIS maps in compliancy with the INSPIRE directives #2420
no deviations to report
- Algorithms are now Generic Resources
NKUA Activities
The beneficiary should report here a summary of the activities performed in the reporting period
The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.
The beneficiary should report here a bullet list highlighting the main achievements of the reporting period
Terradue Activities
- No activity this month due to focus on T10.1
- None
- None
FAO Activities
The beneficiary should report here a summary of the activities performed in the reporting period
The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.
The beneficiary should report here a bullet list highlighting the main achievements of the reporting period
T10.4 Semantic Data Analysis Facilities
FORTH Activities
During this period FORTH worked in constructing the 3rd version of the MarineTLO warehouse. The new warehouse is available at http://virtuoso.i-marine.d4science.org:8890/sparql under the graphspace http://www.ics.forth.gr/isl/TLObasedDataWarehouseV3. The contents of the new warehouse are exploited by the latest version of xsearch-service (1-1-1). Related ticket: #2261
none
Construction of the MarineTLO warehouse V3.
FAO Activities
The beneficiary should report here a summary of the activities performed in the reporting period
The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.
The beneficiary should report here a bullet list highlighting the main achievements of the reporting period