2013.06 WP8: iMarine Data e-Infrastructure Enabling Technology Development Monthly Activity By Task and Beneficiary

From IMarine Wiki

Jump to: navigation, search

Contents

This WP8 Activity Report described the activities performed in June 2013 by Beneficiary and Task.

It is part of June Monthly Activity Report.

T8.1 iMarine Data e-Infrastructure Enabling-technology Development

CNR Activities

  • Started to investigate on a solution in order to deliver software update capability in the infrastructure. Resource Manager and Deployer component dynamics were studied in order to address this issue.
  • Delivered a prototype implementation of the Deployer component that is able to update gCube services. The solution was tested succesfully without taking into account integration with the Resource Manager. The solution will probably be delivered in gCube 2.17 (#554).


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FAO Activities

  • In collaboration with CNR, FAO ha resumed development activities on common-ghn-service, the new facilities to integrate non-gCore Servlet based applications in the infrastructure;
  • FAO has prepared with CNR a presentation on the current state of the previous activity, co-delivering it.
  • FAO has upgraded common-gcore-stubs to version 1.1.0, to fix a bug that prevented WSDL retrieval failures to show.


None to report.


None to report.

T8.2 iMarine Data e-Infrastructure Policy-oriented Security Facilities

E-IIS Activities

During the month of June E-IIS has:

  • prepared and took part to the 6Th TCOM in Skiathos, where has presented the work on the three topics that has in charge (authZ, accounting and portlets) to provide the partners with further information for completing the integration (#1747 and #1718)
  • continued the implementation of the common-accounting library: The status of this activity is reported by the ticket #1582
  • continued the implementation of the accounting portlet. The status of this activity is reported by the ticket #1631


Due to the new requirements devised in May it has been considered necessary to re-engineer the porlet (following the MVP pattern) in order to reduce the overall complexity: anyway this should not impact on the deadlines


None to be reported

T8.3 Workflow Management Facilities

NKUA Activities

During the month of June, we developed a gCube service and its corresponding client to expose the functionality of the previously created workflow adaptor, which handles the execution of workflows of jobs over a variety of processing infrastructures. Moreover, we extended this workflow adaptor to add support for submitting jobs using gJDL to Hadoop and Condor as well (#1276).


none


none

FAO Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T8.4 Resource Model

Complete (the Task was active from M1 to M8)