This WP5 Activity Report described the activities performed in Month 14 by Beneficiary and Task.

It is part of Monthly Activity Report.

T5.1 iMarine Data e-Infrastructure Operation

CERN Activities

The Infrastructure has been upgraded to gCube 2.11.1. The maintenance release was deployed in order to fix some issues in the infrastructure and at portal level. CERN coordinated the upgrade by preparing as well the upgrade plan.

CERN continued also to support the NAS/ISOFTS group in order to upgrade their gCube Infrastructure, activity started at the end of the reporting period.


None


Infrastructure upgrade to gCube 2.11.1

CNR Activities

  • New node to provide service and storage for simple link previews.


None


None

T5.2 iMarine Data e-Infrastructure Nodes Provision

CNR Activities

  • CNR has been keeping up and running the provided nodes hosting GHNs, UMD and project management services.
  • New Production host for the Statistical Manager.
  • Hadoop infrastructure has been doubled (13+13 nodes plus management). The new VMs will be initially used to test new configurations.


None


None

NKUA Activities

NKUA has been keeping up and running the provided nodes hosting GHNs, UMD and the gcube wiki. Any issues and tickets have been resolved immediately. During this period we encountered a disk failure which caused a downtime for 2 VMs. The disk was changed and the VMs was operational again in few hours. Additionally we changed the way that the gcube wiki can be accessed, show that is accessible using both http and https, except of the login page that remains accessible only using secure connection


none


  • Maintained the provided infrastructure operational
  • Maintained gcube wiki operational
  • Successfully replaced broken hard disk that was hosting dl20.di.uoa.gr and dl21.di.uoa.gr VMs and moved them to new hard disk.
  • Changed access to gcube wiki so that is accessible using both http and https, but kept login page accessible only using https

FAO Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FIN Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T5.3 iMarine Data Infrastructure Availability, Monitoring and Accounting

CERN Activities

The Portal Accounting portlet has been refactored to maven and GXT and enhanced as described in:

https://issue.i-marine.research-infrastructures.eu/ticket/67

The component is going to be released for gCube 2.12.0