2012.11 WP5: iMarine Data e-Infrastructure Deployment and Operation Monthly Activity By Task and Beneficiary

From IMarine Wiki

Jump to: navigation, search

Contents

This WP5 Activity Report described the activities performed in November 2012 by Beneficiary and Task.

It is part of Monthly Activity Report.

T5.1 iMarine Data e-Infrastructure Operation

CERN Activities

CERN coordinated the infrastructure support activities, monitoring the resolution of production support tickets.

CERN was also responsible to present the activities of WP5/WP6/WP7 during the first project review held the 6 of november.

The following activities have been completed as well related to maven integration:


None


None

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T5.2 iMarine Data e-Infrastructure Nodes Provision

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

NKUA Activities

NKUA has been keeping up and running the provided nodes hosting GHNs, UMD and the gcube wiki. Any issues and tickets have been resolved immediately.


none


  • Maintained the provided infrastructure operational
  • Maintained gcube wiki operational
  • Successfully resolved all issues/tickets that occured

FAO Activities

The iMarine node was maintained.


None to report.


Node performed flawlessly.

FIN Activities

No activity to be reported. Still no server availability in GEOMAR for the moment.

T5.3 iMarine Data Infrastructure Availability, Monitoring and Accounting

CERN Activities

During the reporting period the following activities have been performed:


None


None