This WP3 Activity Report described the activities performed in November 2012 by Beneficiary and Task.

It is part of Monthly Activity Report.

T3.1 User Community Mediation

FAO Activities

FAO participated to the iMarine review in Brussels.

In the mediation task, FAO continued to engage with the EA-CoP. examples are

  • The FishFinder group that is interested in receiving a VRE for Species Fact Sheets.
  • The Cotrix collaboration shaping with the VocBench group in FAO
  • FLOD dissemination activity


None to report in this Month.


D3.4 on validation was produced.

ERCIM Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

Terradue Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FIN Activities

Reported the proposition made by Lino during the Board meeting in Rome to the Catalogue of Life Global Team meeting to host the CoL webservices in the infrastructure. The IT Group of CoL has to discuss about the proposal but it was welcome. To be followed up at the beginning of 2013.

Rainer Froese is interested to integrate Bayesian statistics for Fisheries management using the R implementation in the infrastructure (through the European Project EcoKnows, www.ecoknows.eu). To be followed when the algorithm is ready.

Attended by Skype the presentation of the Biodiversity Cluster during the EC review.

Discussed with Vanderlei Caminhos to finalize the CRIA activities during the second period.
Met with Ward Appeltans and Edward vanden Berghe in Oostende to finalize their activities during the second period. Summary of discussion to be disseminated for the next SG discussion.

Attended the OBIS Steering Group meeting and mention several times the infrastructure and its capacities. iMarine was well mentioned in the report delivered by Ward. Also Bruno Danis (co-chair of the OBIS SG and ex project manager of SCAR-Marbin) gave a nice presentation on the communication tools used by OBIS. We could review that presentation with TRUST-IT to check if we could engage in a non-explored technology yet.

Nicolas on sick leave the full last week of November.

UNESCO Activities

Preparation (rehearsal) and attending the iMarine review meeting
Promoting the VREs (ecological niche modeling) through twitter and linkedin




IRD Activities

New page on the wiki to describe the semantic cluster activities [1].


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T3.2 Governance Mechanisms, Policies and Guidelines Development

FAO Activities

The Feed-back period for the iMarine Board Meeting 2 closed, and in this reporting period the reporting was performed.


The report of the iMB2 is delayed.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

ERCIM Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FIN Activities

Following up with Donatella the establishment of the MoU with CoL, but the work is reported early 2013 as it seems.

UNESCO Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CRIA Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

IRD Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T3.3 Harmonisation of Metadata, Semantics and Technologies

FAO Activities

Activities continued on:

  • FLOD; mainly defining the TLO and preparing data.
  • SPREAD; discussion the implementation of the re-allocation algorithm and the data discovery across infrastructures.
  • Cotrix; discussions with the VocBench team to align activities in a work-plan. Prepare contract for developer.

Requirements collection and validation of outputs involved staff from FAO, FIN, CRIA, IOC/Unesco


D3.4 was delayed a few days due to late interventions that required clarifications.


D3.4 was produced.

CNR Activities

  • Contribution to deliverable D3.4 EA-CoP Validation.


N/A


NKUA Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FORTH Activities

The TLO-Development activity has recently been planned to follow the six sub-activities (or tasks) described here http://wiki.i-marine.eu/index.php/Top_Level_Ontology. As the process of developing the TLO ontology is based on an Iterative and Incremental development approach (we will have more than one iteration for each involved task), we have focused on an ontological analysis of FLOD and ECOSCOPE and reporting what has been observed and investigated.


none


none

Terradue Activities

Terradue reviewed the Visualization document provided by FAO (E. Blondel). The comments will be integrated in a next draft, mainly focused on improving the existing services that are already provided by the e-infra for data discovery and access. Terradue also suggested the inclusion of R as an approach to visualize raw and aggregated data from time-series, preferably through the e-infrastructure. The approach has been prototyped with the R code provided by IRD. Terradue furthermore initiated an open discussion on the support of legacy applications on the WPS-hadoop framework. Several legacy applications very useful for the environmental contextualization are written in IDL (e.g. IRD legacy applications). Terradue started to investigate on the how iMarine deals with legacy applications.



None.


Comments to visualization approach and techniques.

UNESCO Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CRIA Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

IRD Activities

Work on metadata standards for geospatial cluster: 19115 and 19119 (19139) as a way describe data sources and related services. CSW as a way to enable iMarine infrastructure to harvest IRD data. Technology watch on WPS for R and IDL processings. Technology watch on quadstore mechanisms in Jena (in progress)


Update of previous metadata to share a common approach with FAO.


A first WPS (R code) has been shared and validated with Terradue. This will be used for other R codes.