T11.1 Application Programming Interfaces Framework Definition

NKUA Activities

NKUA has provided FORTH with instructions on integrating the xSearch web application in ASL HTTP Framework and adopting the context management mechanisms provided by the common tools it offers (https://issue.imarine.research-infrastructures.eu/ticket/840).


none


none

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CERN Activities

Nothing to report

E-IIS Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FAO Activities

FAO has handled small bugs in common-gcore-clients and prepared it for the next release of gCF 1.6.0. The fixes are included in version 2.0.2 released with gCube 2.11.1.


None to report.


None to report.

T11.2 Data Management APIs

FAO Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

NKUA Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CERN Activities

A new version of the DataTransfer Agent CL has been implemented ( v 1.2.0-SNAPSHOT) in order to implement some enhancements:

In addition some bug fixes have been performed.

A new version of the the DataTransfer Scheduler Service CL has been also implemented ( 1.1.0-SNAPSHOT) with fixes and enhancements:


None


none

E-IIS Activities

E-IIS started the testing of common-security library on E-IIS testbed and completed the test of authentication feature (client side), according to the ticket #341. It is now starting the testing of the SOA3/gCube integration, which is the gCube Security Handler, according to the ticket #376.


None to report.


None to report.

FORTH Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

Terradue Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T11.3 Data Consumption APIs

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

NKUA Activities

An implementation of a client library for Data Transformation Service (#841) has been completed, based on client-library framework. More specifically, Data Transformation Service API is exposed to the client, while hiding probably frustrating complexity from the client. NKUA has also started the design and implementation of a client library for submitting jobs over the JDL adaptor of the Execution engine.


none


Implementation of the following library has been completed:

  • dts-gcore-client-lib

FORTH Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

Terradue Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FAO Activities

The beneficiary should report here a summary of the activities performed in the reporting period