This WP3 Activity Report described the activities performed in August 2012 by Beneficiary and Task.

It is part of August 2012 Monthly Activity Report.

T3.1 User Community Mediation

FAO Activities

The actions performed include;

  • Preparations for the iMarine Board meeting in Rome in October
  • Meetings with other project such as through IOC / UNESCO, CRIA
  • Interactions with FAO potential VRE beneficiaries; FishFinder and Tuna Atlas
  • Discussed potential collaboration on code list management development


None to report


ERCIM Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

Terradue Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FIN Activities

Preparation of the TDWG conference with colleagues from the Chinese Academy of Fisheries Sciences.

Outline of a paper about testing AquaMaps on a real case, the Lessepsian migrants from Red Sea to Mediterranean (and the reverse although they are only a few). All maps and computations will be done under the infrastructure, including statistical analyses with the dedicated VRE in order to re-mobilize the AquaMaps community that is waiting for a new run with an additional climate change scenario. We also hope that a publication with the description of the VRE in the Material and Method section will help to increase the visibility of the infra-structure.


The re-run was delayed since February by two facts, see WP6 section T6.2.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

UNESCO Activities

On 28 August 2012, the OBIS’ secretariat at UNESCO’s IOC project office for IODE in Oostende hosted a meeting between the iMarine managers (Donatella Castelli, Pasquale Pagano and Anton Ellenbroek), OBIS (Ward Appeltans, Aditya Naik Kakodkar) and several people at the Flanders Marine Institute (VLIZ). VLIZ is hosting the OBIS and WoRMS databases and webservers and is involved in several important marine biodiversity projects (EMODNET, EuroMarine, LifeWatch, etc…). It was a fruitful meeting because we could identify a number of synergies and topics on which we can collaborate in the future, e.g., adding the OBIS webserver as a new node within the iMarine GRID infrastructure or sharing resources and developments, e.g., webservices. To formalize these agreements, the details on data access, terms of use and technical arrangements will be outlined in a Memorandum of Understanding.

Together with FIN (via skype calls), OBIS is also contributing to the preparation of the taxon name reconciliation process within the biodiversity cluster.


none


Important steps are taken to provide access to the OBIS and WoRMS databases.

IRD Activities

The beneficiary should report here a summary of the activities performed in the reporting period


IRD is preparing its participation to the geospatial cluster (in october). Discussions with CNR, FAO and other partners have been really usefull to clarify how we will join this cluster (about (meta)data formats and protocols). Same with fisheries data (Fishframe and elogbooks).


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T3.2 Governance Mechanisms, Policies and Guidelines Development

FAO Activities

The Governance pages on the iMarine Wiki have been further edited by the iMarine chair, as contribution to D3.2 and for review by iMarine Board members and discussion at Board2 meeting.


  • Governance pages on the iMarine Wiki in draft 1 stage
  • D3.2 TOC and draft 1 circulated

ERCIM Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CNR Activities

  • Feedback on first draft version of the "EA-CoP Data Access and Sharing Policies" document


None to report.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FIN Activities

Nicolas sent 2 models of Memorandum of Understanding to Marc and Anton to support further discussions (FishBase Consortium, EcoPath Consortium), with an email with some possible orientations (July).

Nicolas had a long discussion with Marc to comment these possible orientations, and how to proceed further.

Nicolas attended part of the discussions with VLIZ/IODE. And had later a discussion with Ward to precise the content of the name reconciliation exercise. Requirements document to be prepared for the TCOM last.

UNESCO Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CRIA Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

IRD Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T3.3 Harmonisation of Metadata, Semantics and Technologies

FAO Activities

Activities continued on SPREAD (.8 PM) and FLOD.

Validation of existing tools continued for the Tuna Atlas and ICIS cases.

The requirements collection and use case development for a code list manager continued, including activities to contract a JAVA developer.

An informal discussion was organized with BoI on their efforts to Open Source their SDMX tools; there is now a document submitted for management approval. In addition, BoI has developed capacity to e.g. convert Excel to SDMX.


None to report.


In several cluster calls, the scenario for the biodiversity cluster was further detailed. There has been a change of representation in the IOC / UNESCO group, which has now produced first requirements.

CNR Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

NKUA Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

FORTH Activities

FORTH continued the work on TLO based on the analysis of the material sent by FAO and IRD.


none


none

Terradue Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

UNESCO Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

CRIA Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

IRD Activities

The beneficiary should report here a summary of the activities performed in the reporting period


For semantic cluster, IRD has been working on setting up opensearch protocol to enable data discovery on Ecoscope Knowledge Base (X-Search, CSW3 if possible). A first demo should be available in october. Some work on top level ontology aims to define the first set of classes and properties shared by FAO and IRD.


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period