This WP2 Activity Report described the activities performed in March 2012 by Beneficiary and Task.

It is part of the March 2012 Activity Report.

T2.1 Scientific Coordination

CNR Activities

  • Monitoring and supervision of scientific activities and deliverables in the period;
  • Organization of monthly SB (6 March 2012) teleconference and review of the corresponding minutes prepared by ERCIM;
  • Representation of the project at ICRI2012 (21-23 March, 2012, Copenhagen) and at the D4Life final workshop (28-29 March, 2012, Reading (UK);
  • On-going discussion with representatives of the ScienceSoft initiative.


No major deviation.


  • Monitoring and supervision of scientific activities and deliverables in the period;
  • Organization of monthly SB (6 March 2012) teleconference;
  • Establishment of liaisons with a number of EU projects in the marine and biodiversity areas (e.g. EUROMarine, JPI Oceans, OCEANS)

T2.2 Project Strategy

CNR Activities

The replacement of Frank Bisby in the iMarine Board was discussed with FAO and with Sp2000 representatives.


No major deviation.


  • Identification of a list of names of potential replacements of Frank Bisby in the iMarine Board.

FAO Activities

At project management level, FAO consulted it's CoP to provide input through the project governance mechanisms; the iMarine advisory council and the imarine Board Meeting were strategically discussed and prepared with high-level advisors from both bodies and beyond.


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period

T2.3 Executive Management

CNR Activities

  • Organization of the monthly PEB on 4 March 2012 and preparation of the meeting minutes ;
  • Monitoring and replanning of the technical activities;
  • Organisation and chairing of the Second f2f TCom on14-16 March 2012 in Rome.


No major deviation.


  • Monthly PEB on 4 March 2012;
  • Monitoring and replanning of the technical activities;
  • Second f2f TCom on 14-16 March 2012 in Rome.

NKUA Activities

The beneficiary should report here a summary of the activities performed in the reporting period


The beneficiary should report here major issues faced in the reporting period and the identified corrective actions, if any.


The beneficiary should report here a bullet list highlighting the main achievements of the reporting period